Red Beech Farmhouse
ARCHITECTS PRACTICE – NATIONAL TRUST
CLIENT – NATIONAL TRUST
FUNDED BY – NATIONAL TRUST
CONTRACT SUM – £225’000.00
CONTRACT PERIOD – 24 WEEKS
CLIENT – NATIONAL TRUST
FUNDED BY – NATIONAL TRUST
CONTRACT SUM – £225’000.00
CONTRACT PERIOD – 24 WEEKS
THE WORKS ARE TO FULLY REFURBISH THE FARMHOUSE, THIS CONSTISTS OF A FULL STRIP OUT, REMOVAL OF PLASTER FROM EXTERNAL WALLS, REPLASTERING WITH AN INSULATED PLASTER.
FULL MECHANICAL AND ELECTRICAL INSTALLATION ALONG WITH AIR SOURCE HEAT PUMP.
INSTALLATION OF A SEWAGE TREATMENT PLANT
REMOVAL OF STRUCTURAL WALLS TO OPEN UP KITCHEN AREA.
FITTING OF NEW KITCHEN AND UTILITY.
TAKE DOWN OF OUTBUILDING AND PORCH THEN REBUILD.